BUNDABERG AIRPORT 2008 $19 mill  

BALLINA   LORD HOWE   KARRATHA   ONSLOW   LONGREACH   WHITSUNDAY   EMERALD   BUNDABERG   ROCKHAMPTON   SUNSHINE COAST

STEA Astute Architecture Airport Design Bundaberg Airport

STEA Astute Architecture Airport Design Bundaberg Airport

STEA Astute Architecture Airport Design Bundaberg Airport

 

Stea were appointed as Principal Consultant for the $19 million new development including aprons, carparks and  a standalone 3,000 m² terminal. Due to the amalagation of  regional councils this project did not proceed.We were subsequently commissioned  for the redevelopment of the existing terminal.

We delivered the project within the specified 12 week construction period, with final gross project costs $100k under the agreed budget.